ABSTRACT:- A substation is a part of an
electrical generation, transmission,and distribution syst
em. Substations transform voltage from high to low, or
the reverse, or perform any of several other important
functions. Between the generating station and consumer,
electric power may flow through several substations at
different voltage levels. Substations may be owned and
operated by an electrical utility, or may be owned by a
large industrial or commercial customer. Generally
substations are unattended, relying on SCADA for
remote supervision and control.
A substation may include transformers to change
voltage levels between high transmission voltages and
lower distribution voltages, or at the interconnection of
two different transmission voltages. The
word substation comes from the days before the
distribution system became a grid. As central generation
stations became larger, smaller generating plants were
converted to distribution stations, receiving their energy
supply from a larger plant instead of using their own
generators. The first substations were connected to only
one power station, where the generators were housed,
and were subsidiaries of that power station.
Index terms:-
Substation location, substation
grounding, Scada system
I. INTRODUCTION
In electricity supply systems, an earthing (grounding)
system defines the electrical potential of the conductors
relative to that of the Earth's conductive surface. The choice
of earthing system has implications for the safety and
electromagnetic compatibility of the power supply. Note
that regulations for earthing systems vary considerably
between different countries. A functional earth connection
serves a purpose other than providing protection against
electrical shock. In contrast to a protective earth connection,
a functional earth connection may carry a current during the
normal operation of a device. Functional earth connections
may be required by devices such as surge suppression and
electromagnetic-compatibility filters, some types of
antennas and various measurement instruments. Generally
the protective earth is also used as a functional earth, though
this requires care in some situations. Safety and reliability
are the two major concerns in the operation and design of an
electrical power system. These concerns also pertain to the
design of substations. To ensure that substations are safe
and reliable, the substation must have a properly designed
grounding system.
SCADA (supervisory control and data acquisition) is a
system operating with coded signals over communication
channels so as to provide control of remote equipment
(using typically one communication channel per remote
station).
It is a type of industrial control system (ICS). Industrial
control systems are computer-based systems that monitor
and control industrial processes that exist in the physical
world. SCADA systems historically distinguish themselves
from other ICS systems by being large-scale processes that
can include multiple sites, and large distances. These
processes include industrial, infrastructure, and facilitybased
processes.
1. Industrial processes include those of
manufacturing, production, power
generation, fabrication, and refining, and may run in
continuous, batch, repetitive, or discrete modes.
2. Infrastructure processes may be public or private,
and include water treatment and distribution,
wastewater collection and treatment, oil and gas
pipelines, electrical power
2 | P a g e
transmission and distribution, wind farms, civil defense
siren systems, and large communication systems.
3. Facility processes occur both in public facilities
and private ones, including buildings, airports, ships,
and space stations. They monitor and control heating,
ventilation, and air conditioning systems
(HVAC), access, and energy consumption. The term
SCADA usually refers to centralized systems which
monitor and control entire sites, or complexes of
systems spread out over large areas (anything from an
industrial plant to a nation). Most control actions are
performed automatically by RTUs or by PLCs. Host
control functions are usually restricted to basic
overriding or supervisory level intervention.
II. SUBSTATION AND OPERATION
The two main design goals to be achieved by any substation
ground system under both normal and fault conditions are:
1. To provide means to dissipate electric currents into the
earth without exceeding any operating and equipment limits
2. To assure that a person in the vicinity of grounded
facilities is not exposed to the danger of critical electric
shock
Grounding is an important aspect of every substation. The
function of a grounding system is: to ensure the safety of
personnel and the public, to minimize hazard from
transferred potential, to protect equipment, to provide a
discharge path for lightning strikes, and to provide a lowresistance
path to ground. A good grounding system has a
low resistance to remote earth to minimize the ground
potential rise.
This second generation of transformer substations was also
the subject of the first internal fault tests, intended to
provide operating personnel and the general public with
greater levels of safety. The next step was the introduction
of factory assembled prefabricated transformer substations.
The Substation was founded in September 1990 by theatre
director and writer, Kuo Pao Kun. The centre derives its
name from the conservation building which it now occupies.
Constructed in 1926, the building was formerly a power
substation.
The idea of an independent arts centre first came to Kuo in
December 1985. He envisioned the future of the then
abandoned power substation as a place where people could
gather to interact and engage with different arts forms. n
collaboration with renowned architect Tay Kheng Soon
(who later became the Founding Chairman of the centre), a
proposal for the arts centre was created and subsequently
submitted to Ministry of Community Development (MCD).
The centre was awarded $1.07 million by the MCD in 1989
for the reconstruction of the building. The renovation was
completed in June 1990, and the centre was officially
opened on 16 September 1990 by then Minister of
Community Development, Mr Wong Kan Seng. Kuo was
artistic director of the centre from its founding to 1995. He
was succeeded by T. Sasitharan. Since 2000, the co-artistic
directors are Audrey Wong and Lee Weng Choy.
There are many parameters that have an effect on the
voltages in and around the substation area. Since voltages
are site-dependent, it is impossible to design one grounding
system that is acceptable for all locations. The grid current,
fault duration, soil resistivity, surface material, and the size
and shape of the grid all have a substantial effect on the
voltages in and around the substation area. If the geometry,
location of ground electrodes, local soil characteristics, and
other factors contribute to an excessive potential gradient at
the earth surface, the grounding system may be inadequate
from a safety aspect despite its capacity to carry the fault
current in magnitudes and durations permitted by protective
relays.
During typical ground fault conditions, unless proper
precautions are taken in design, the maximum potential
gradients along the earth surface may be of sufficient
magnitude to endanger a person in the area.
III. OPERATING TYPES
Beauly:- Relocation of the existing substation was
discounted by SHETL due to the requirement for a large site
and associated redirection of towers and overhead lines.
Similarly, construction of an additional substation remote
from the existing Beauly Substation was considered to have
greater environmental impact and disruption than expansion
of the existing facility.
The decision to extend the existing Beauly Substation into
former quarry land adjacent to the site meets the
requirements of being close to the existing site and allowing
smooth integration of the new electrical circuits into the
existing network. This option also avoids the disruption and
potential environmental impacts associated with closure of
the site and redevelopment of a large new substation site in
a different location. The preferred substation site is located
on the southern edge of the community of Wester Balblair ,
2km south west of Beauly.
Fasnakyle:- A number of options for new substation sites in
the vicinity of the existing substation at Fasnakyle were
examined. Each was considered potentially to result in
greater environmental impact than the preferred option
3 | P a g e
which would be to redevelop the existing substation site to
provide an upgraded facility.
The decision to construct the new substation on the site of
the existing substation avoids the use of a new site and
allows for the smooth integration of the new electrical
circuits into the existing networks. It also avoids the
requirement for overhead or underground cables to link an
alternative site into the existing substation site.
The existing substation site is located in Strathglass, 2km
south west of Cannich.
Fort Augustus:- No alternatives were considered by
SHETL for this substation. The existing substation site
would be sufficient to contain some of the required new
plant. The site would need to be extended to the south onto
land owned by SSE.
Extending the existing site avoids disruption to existing
networks and avoids the environmental impact of creating a
new site. The area proposed for the extension is well
screened and is
presently used for grazing. The existing substation is located
in the settlement of Auchteraw, on a wooded hillside, 2.5km
south west of Fort Austus.
Tummel:- An existing substation, Errochty Substation, is
located on land south of the River Tummel in Tummel
Bridge. Expansion of this site to provide the required new
substation facility was
considered but rejected due to environmental impacts
including loss of woodland and the requirement to route
transmission lines over a nearby holiday park. Relocation of
the Errochty Substation to a new site which could
incorporate the requirements for the new transmission line
was also considered, but again rejected on environmental
and technical grounds due to the disruption involved in
relocating many overhead and underground lines and
significant earthworks required for the nearest feasible site
at Tummel Workshop.
Proposed Beauly to Denny 400kV Overhead Transmission
Line Substation Site Selection The preferred option would
therefore be to construct a new substation at the Tummel
Workshop site and provide a connection to the nearby
Errochty Substation via the two 132kV underground cables.
The area at Tummel Workshop has been used historically as
a construction compound during previous construction
works in the area: it has sufficient flat ground for the
proposed substation and is screened by existing trees.
Tummel Workshop site is approximately 0.5km west of the
settlement of Tummel Bridge on
the southern side of the River Tummel.
Braco
Several alternative sites for the development of a new
substation site were considered. The choice of sites was
limited by the key criteria that the new substation must be
along the route of, or close to, the proposed transmission
line and relatively close to the existing substation to
facilitate reconnection of electrical circuits.
Whilst a number of alternative sites were considered,
environmental issues and site conditions narrowed down the
available options to a preferred new Braco Substation. This
would be constructed at a site which allows connection both
to the overhead transmission line and existing overhead line
circuits as well as the underground cable circuits to the
Braes of Doune windfarm. It would also allow the existing
Braco Substation, which is situated within an area of
archaeological interest, to be removed.
The proposed new substation would be located on a site 4
km west of Braco (and 4.5km west
southwest of the present Braco Substation) on land that is
currently occupied by commercial
forestry:-
Denny North:- At present the Denny North site is a strategic
junction in electrical transmission network where five
existing 275kV and two 132kV overhead lines converge.
The proposed site offers a
location where no new overhead lines or extensive
deviations of the existing network would be required to
accommodate the construction of the new substation and
connection of the Beauly to Denny 400kV overhead line
into the existing network. Denny North Substation site is
located in a rural area 2km north of Denny.
substation grounding:-
1. Unearthed Systems:
It is used no more. The neutral is not connected to the earth,
also called as insulated neutral system.
Solid grounding or effective grounding:
The neutral is directly connected to the earth without any
impedance between neutral and ground.
Resistance grounding:-
Resistance is connected between the neutral and the ground.
Reactance grounding:-
Reactance is connected between the neutral and ground.
Resonant Grounding:-
An adjustable reactor of correctly selected value to
compensate the capacitive earth current is connected
between the neutral and the earth. The coil is called Arc
Suppression Coil or Earth Fault Neutralizer.
Scada systems
4 | P a g e
B. Early or Monolithic SCADA systems
1. The first SCADA systems held all operations in one,
usually a mainframe, computer. There was little control
exercised, and most early SCADA functions were limited to
monitoring sensors and flagging any operations which
exceeded programmed alarm levels. These systems were all
vendor-proprietary software and usually limited to a single
plant or facility. Like the software, SCADA hardware from
one vendor was rarely usable in another vendor's SCADA
system.
C. Distributed SCADA Systems
1. Later SCADA systems became known as Distributed
systems since they often shared control functions across
multiple smaller (usually PC) computers connected by Local
Area Networks (LAN). Using LAN, these individual
stations shared Real Time information and often performed
small control tasks in addition to alerting operators of
possible problems or tripped alarm levels.
Networked SCADA systems
Current SCADA systems are usually networked. They
communicate through Wide Area Networks (WAN)
systems, over phone or data lines and often transmit data
between nodes through Ethernet or Fiber Optic connections.
Networked SCADA systems make heavy use of
Programmable Logic Controllers (PLC) to monitor and
make routine process adjustments, only flagging Operators
when major decisions are required.
Unlike earlier SCADA systems, which primarily used
vendor-proprietary software and sometimes hardware,
current systems are based on more general use software.
The hardware tends to be more interchangeable as PLC and
other sub-unit vendors have standardized communications
and other protocols to allow the user to choose the best
component for their needs rather than being tied to one
vendor's line of products.
While earlier SCADA systems were limited to single
building or sometimes single site networks, many
current SCADA systems connect to the Internet, which
raises security risks not seen with older or "sealed"
systems.
IV. RESEARCH AND
DEVELOPMENTS
Substation location:- A Strong and Smart Grid is the
development direction and established target of future grid
in China. In respect that Smart Substation is the principal
foundation and support of Smart Grid, the research on key
technologies about Smart substations has attracted an
increasing amount of attention in the recent years. In this
paper, we demonstrate the latest concept, strategy and
objective of State Grid for the development of smart
substation. Meanwhile, we present our latest research on
technologies in Smart Substation .The new West Substation
will be located on the west side of the Social Sciences
Centre (SSC), between the building’s parking lot and the
University Community Centre (UCC). The substation will
expand on an existing smaller substation, currently located
at the site and servicing only the SSC. Construction on the
$3.5-million project will begin this month or next with the
expectation of it being operational by December or January.
This need, Cote continued, is all about supply and demand.
Currently, Western’s core campus is served by three London
Hydro-fed, yet university-owned, substations – North
Substation, located in the University Hospital area; East
Substation, located between the Visual Arts and Chemistry
buildings’ parking lots; and South Substation, located
behind Alumni Hall. North and East were constructed in
1993, followed by South in 2002.
Substation Grounding:- An investigation into the optimal
design of a substation grounding system for the transmission
substation in Gaza City, Palestine has been carried out. A
research into the most influential parameters on the
effective- ness of the substation grid system has been
performed and its results have been incorporated into the
Gaza case study. Through modelling and simulating the
power station in Gaza while considering some field data, an
optimal substation grounding grid has been designed and
has shown complete conformance to safety. It is thus
considered that such a design will protect personnel in any
area of the substation in addition to the in-stalled machinery
if the largest possible fault current was to traverse the earth.
scada systems:- The current development of data acquisition
technology. The various practical considerations in applying
Data Acquisition Systems are summarized, and some
feasible areas of advanced applications are investigated.
5 | P a g e
Javaenabled mobile as a client in a sample SCADA
application in order to display and supervise the position of
a sample prototype crane. The wireless communication
between the mobile phone and the SCADA server is
performed by means of a base station via general packet
radio service GPRS and wireless application protocol WAP.
Test results have indicated that the mobile phone based
SCADA integration using the GPRS or WAP transfer
scheme could enhance the performance of the crane in a day
without causing an increase in the response times of
SCADA functions.
broad overview of cyber security and risk assessment for
SCADA and DCS, have introduced the main industry
organizations and government groups working in this area,
and have given a comprehensive review of the literature to
date. Presented in broad terms is probability risk analysis
which includes methods such as FTA, ETA, and FMEA.
The authors have concluded with a general discussion of
two recent methods that quantitatively determine the
probability of an attack, the impact of the attack, and the
reduction in risk associated with a particular
countermeasure.
V. CONCLUSION
In this term I have shows the how to ground the substation
and location of substation also required and wealso discuss
the scada systems.
In this term paper we have shown that different type of
location and different type of grounding like resistence ,
reactance and resonanat grounding.and different type of
scada system used in that type also used .
the recent lead SCADA Security Instructor for InfoSec
Institute, and having been involved in the ICS security
industry for several years, I have quickly realized that there
is a shortfall in training to address how to secure industrial
control systems like Supervisory Control and Data
Acquisition (SCADA) and Distributed Control Systems
(DCS). There are several very good courses currently
available,however, when reviewing the syllabi of these
courses, it becomes clear that they tend to focus too much
on either theoretical aspects of the problem, or
the hacking or red team side of ICS security.
VI. REFERENCES
1. IEEE, “IEEE Recommended Practice for
Determining the Electric Power Station Ground